The Berkeley Square Manchester, spearheaded by the Heaton Group, is making remarkable progress, as highlighted in their latest April 2025 update. This ambitious project is shaping up to be a premier residential complex, blending modern design with high-quality construction standards. Here’s a detailed look at the latest updates and milestones achieved.
External Progress
The façade work is advancing steadily, with the brick slip system being applied across all elevations. As sections are completed, they are handed over for the installation of window sills, mastic works, and Juliette balconies. The removal of mast climbers has also begun, paving the way for scaffolding to come down soon. These developments mark significant strides in the external appearance of the building, bringing it closer to its final look.
Internal Developments
Inside the building, progress is equally impressive. Partition work is moving ahead on levels 6 to 8, while mechanical, electrical, and plumbing (MEP) second and final fixes have reached level 4. First fixes are complete up to level 8. Floor finishes and painting are underway on level 6, with kitchens, tiling, and joinery progressing on level 5. Apartments on level 4 are undergoing final decoration, and snagging continues on level 1. Impressively, 38 apartments are now fully complete and ready for inspection.
Utilities and Infrastructure
All lifts have been installed, and commissioning has started. Water is now live within the building, but the permanent power connection has been delayed due to off-site challenges, including the unexpected discovery of a redundant rail tunnel. The power connection is now anticipated by early August. Despite this setback, the project remains ahead of schedule by five weeks, a testament to the efficiency and dedication of the construction team.
Testing and Compliance
Quality assurance remains a top priority. Air tests for 59 apartments have all passed, maintaining a strong average of 2.72. Acoustic testing is halfway complete, with excellent feedback on build quality. These results underscore the commitment to delivering a high-standard living environment for future residents.
Upcoming Focus Areas
Looking ahead, the focus for May includes continuing façade works and starting balcony installations. Internal fit-outs on levels 4 and 5 will advance, along with ongoing snagging. Lift commissioning will be finalized, and scaffold removal will begin, preparing the site for landscaping phases. These tasks are crucial for transitioning the project into its final stages.
Design and Safety
The design team has been refining key aspects of the project, including roof details, access routes, and wayfinding signage. Safety remains a priority, with no major incidents reported. Minor audit actions are being addressed to ensure a safe working environment. Quality checks continue across all trades, ensuring that the high standards set by the Heaton Group are consistently met.
Despite challenges such as the delay in the power connection, the Berkeley Square development is progressing at an impressive pace. With fit-outs advancing and balconies on the horizon, the project is entering an exciting phase. The Heaton Group’s commitment to quality and efficiency is evident in every aspect of this development, promising a premier residential experience in the heart of Manchester.
Just announced – show apartment has been completed.
This update showcases the meticulous planning and execution that define the Berkeley Square Manchester project. As the development moves closer to completion, it stands as a testament to the Heaton Group’s expertise and dedication to excellence. Stay tuned for more updates as this landmark project continues to take shape.